|
This lecture reviews the critical path method.
Project management software generally calculate the critical path, so most
students do not need to do so by hand. This lecture provides you with
insight on how the software establishes the critical path.
- Understand calculation of earliest start and finish times
- Calculate the slack time for each activity
- Identify the critical path
- Examine impact of splitting an activity
- Communicate schedules to others
- The critical path methods as a quality tool.
More►
- Lecture on critical path method.
Slides►
Listen►
SWF►
You
Tube 1►
You
Tube 2►
Arabic 1►
Arabic 2►
- Lecture on estimating duration of an activity
Slides►
Listen►
SWF►
WMV►
Arabic►
Advanced learners like you, often need different ways of understanding a topic. Reading is just one way of understanding. Another way is through writing about what you have
read. The enclosed assessment is designed to get you to think more about the concepts taught in this session.
- What is the relationship between slack and earliest start time?
- What is the relationship between critical path and slack time of
activities?
- What is calculated in the forward pass?
- What is calculated in the backward pass?
- What charts are used to communicate a schedule?
- What is estimate-talk-estimate and how much more accurate is it from
simply having a discussion and then estimating the duration of an
activity?
Please send an email to
your instructor with your responses to the above questions.
Make sure that the email subject line includes the course number, topic name and your name, otherwise it will not get to the right place. If you wish to receive a receipt that the instructor has received your email, you may request the receipt from your email program. Please respond to all of the questions within the same email. Do not attach any files. Keep a copy of all your emails to the instructor till the end of the semester.
Email►
-
Three experts have estimated
the duration of an activity to be 5, 7 and 10 weeks. After
discussion they have revised their estimates to 5, 8 and 9 weeks.
What is your estimate of the duration of this activity?
-
Select two informants to
interview (could be classmates), use the estimate talk estimate
procedure, find out optimistic, realistic and pessimistic estimates of
how long it takes to park a car on or near campus. Describe who
you interviewed, what were their first set of estimates, what was
discussed, and what were their subsequent estimates.
-
In the following three
project network, calculate the earliest start and latest start for each
task. Task are on nodes. Duration of tasks are on arcs
following each task.

-
Given the following table of
activities and precedents, calculate the earliest and latest start and
finish times of the various activities. Report the slack for each
activity. Indicate the activities on the critical path.
Activity |
Description
of Activity |
Immediate
Precedence |
Duration |
Earliest
Start |
Earliest
Finish |
Latest
Start |
Latest Finish |
Slack |
A |
Obtain list of
patients |
|
2 weeks |
1/1/2009 |
|
|
|
|
B |
Sample
patients |
A |
1 week |
|
|
|
|
|
C |
Print survey
tool |
|
3 weeks |
|
|
|
|
|
D |
Mail survey
tool |
B, C |
4 weeks |
|
|
|
|
|
E |
Collect early
responses |
D |
1 week |
|
|
|
|
|
F |
Collect late
responses |
E |
3 weeks |
|
|
|
|
|
G |
Analyze data |
E |
2 weeks |
|
|
|
|
|
H |
Report
findings |
F, G |
1 week |
|
|
|
|
|
-
Calculate the start and end dates for the following
tasks in a healthcare construction project that is supposed to start on
January 1st, 2009. Show which activities are on the critical path.
WBS code |
Description
of Activity |
Immediate
Precedence |
Pessimistic |
Realistic |
Optimistic |
Start |
End |
Critical
path? |
1 |
Strategic plan
phase |
|
9 months |
8 months |
6 months |
1/1/2009 |
|
|
2 |
Project initiation
phase |
1 |
Depends on
duration of sub-tasks |
|
|
|
2.1. |
Team
formation |
|
3 months |
2 months |
1 month |
|
|
|
2.2. |
Master facility plan |
2.1 |
8 months |
7 months |
6 months |
|
|
|
2.3. |
Space
programming |
Finish with 2.2 |
9 months |
7 months |
6 months |
|
|
|
2.4. |
Land
acquisition analysis |
2.2 |
6 months |
4 months |
3 months |
|
|
|
2.5. |
Project budget & schedule |
2.2 |
5 months |
2 months |
1 months |
|
|
|
2.6. |
Joint
venture analysis |
2.1 |
5 months |
2 months |
1 months |
|
|
|
3 |
Building design |
1, 2 |
Depends on
duration of sub-tasks |
|
|
|
3.1. |
Facility design |
|
9 months |
7 months |
6 months |
|
|
|
3.2. |
Equipment planning |
3.1 |
6 months |
4 months |
3 months |
|
|
|
3.3. |
Regulatory approvals |
3.2 |
4 months |
2 months |
1 month |
|
|
|
4 |
Construction phase |
3 |
9 months |
6 months |
5 months |
|
|
|
5 |
Occupancy |
4 |
3 months |
2 months |
1 month |
|
|
|
- Critical path method using Excel
More►
This page is part of the course on Project Management. This page was last edited on
01/31/17 by Farrokh Alemi, Ph.D ©Copyright protected.
|